Elizabeth Towers

Elizabeth Towers

Value

$8.70m

Completion

April 2024

Scope

Full electrical, data and security installation

25 Townhouses

95 Apartments

8000m2 Commercial Spaces

Key Challenges and Outcomes

  • Client Supplied Products – Not managed well by Client or Main Contractor. Aotea took over the management of this aspect.
  • Programme – The programme was accelerated. Aotea were able to increase resources
  • Subcontractor Continuity – With the programme being extended some subcontractors could not complete their contractual requirements. Aotea had the ability to take on this additional scope and provide extra resources as and when required.